Miners could risk $1.5B extra project costs, analysis says

Overruns could add 20% to project costs for the average miner

Horizonte failed to secure full financing for its Araguaia nickel project in Brazil following cost overruns. Credit: Horizonte Minerals

Horizonte failed to secure full financing for its Araguaia nickel project in Brazil following cost overruns. Credit: Horizonte Minerals

Cost overruns could risk around $1.5 billion of capital expenditures each year for the average energy and natural resource company, according to analysis from Bain & Company. Bain analysed capex investment...

Start a free trial to continue reading this article

Already have an account?

Subscribe now

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining News Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining News Intelligence team.

editions

Mining Company ESG Index: Benchmarking the Future of Sustainable Mining

The Mining Company ESG Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Journal Intelligence Global Leadership Report 2024: Net Zero

Gain insights into decarbonisation trends and strategies from interviews with 20+ top mining executives and experts plus an industrywide survey.

editions

Mining Journal Intelligence Project Pipeline Handbook 2024

View our 50 top mining projects, handpicked using a unique, objective selection process from a database of 450+ global assets.

editions

MiningNews.net Research Report 2024

Access a multi-pronged tool to identify critical risks and opportunities in Australia’s mining industry.