PFS delivers 'world-class' SPD development options

Vanadium Resources claims Steelpoortdrift leaves rivals in the dust

 Steelpoortdrift

Steelpoortdrift

Those rivals include Technology Metals Australia and Australian Vanadium's proposed developments at Gabanintha in Western Australia, and Bushveld Mineral's Mokopane project in South Africa.
 
VR8 has been running the ruler over SPD since early 2018, and is moving to finalise its 74% stake in what it claims is shaping as a world-class, large-scale, high-grade, and low-cost operation that will cost just US$200 million to develop, but should generate $5.9 billion in EBITDA over 25 years.
 
Payback for the 1.6 million tonne stage one processing operation is 25 months, based on an average annual free cashflow of $139 million, which could be used to fund an expansion to $147 million in year six to 3.2Mtpa.
 
Stage one involves a mine, concentrator and 720,000tpa conventional salt roast leach processing facility, producing 12,500tpa of flake product at what chairman Jurie Wessels said would be "superior grades" of a 98% vanadium product.
 
The project would produce 39 million pounds per annum vanadium pentoxide over the life of mine at an expected $3.09/lb compared with a forecast price of $9.03/lb. 
 
On a 100% basis, SPD's net present value is estimated at US$1.2 billion, with a post-tax internal rate of return of 45%.
 
The PFS did not examine the benefits of an "eco-friendly" integrated extraction, processing, refining, and manufacturing technology that VR8 is earning an interest in, and which could offer production of battery-grade vanadium pentoxide, and iron, titanium and silicon that are not extracted using conventional processing methods.
 
Wessels said while the PFS was a "giant leap" for SPD, the definitive feasibility study would examine a number of optimisation opportunities and alternative processing technologies.
 
He said the base case was promising, and offered funding and development flexibility.
 
VR8 hopes to complete the DFS in March 2022, with construction expected to commence in late 2023, and first flake production in early 2024.
 
Shares in the company, which have traded between A1.7-7.8c over the past year jumped almost 15% in early trade to 6.3c, valuing it at almost $23 million.
 
The explorer recently raised $2 million at 4.8c to fund its studies.

 

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining News Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining News Intelligence team.

editions

Mining Company ESG Index: Benchmarking the Future of Sustainable Mining

The Mining Company ESG Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Journal Intelligence Global Leadership Report 2024: Net Zero

Gain insights into decarbonisation trends and strategies from interviews with 20+ top mining executives and experts plus an industrywide survey.

editions

Mining Journal Intelligence Project Pipeline Handbook 2024

View our 50 top mining projects, handpicked using a unique, objective selection process from a database of 450+ global assets.

editions

MiningNews.net Research Report 2024

Access a multi-pronged tool to identify critical risks and opportunities in Australia’s mining industry.