LEADERSHIP

Rainy River on course

US$1b Ontario gold project moves closer to mid-2017 production start

MiningNews.Net
Rainy River on course

RBC Capital Markets analysts who’ve just visited the site say the crucial commissioning and transition to full production at the 21,000 tonnes-per-day Rainy River milling complex – compared with New Afton’s 11,000tpd mill capacity – is in capable hands. The New Afton team saw its albeit smaller circuit into commercial production in only 28 days.

“We note the ramp-up to full production [at Rainy River] is a higher risk phase [of the project’s development], particularly with larger mills,” RBC said in a post-visit note.

“Based on our proprietary database of similar sized ramp-ups, it typically takes 11 quarters to reach steady-state throughput with 60% of design achieved in 1-2 quarters and 80% in 3-4 quarters.

“Once at steady state design levels the [Rainy River] project is expected to nearly double New Gold’s current production at below average costs. In the near term, the project is in the midst of a higher risk phase as construction is completed and project ramp-up begins.”

The usual market malaise around such a pivotal commissioning is in evidence with New Gold, which is shooting for gold production of more than 360,000oz in 2016 from its existing operations in Canada, USA, Mexico and Australia (plus significant silver and copper output). Rainy River, 100%-owned, is slated to add 325,000ozpa to that from FY2019 when Rainy River underground production kicks in (recently delayed by a year).

The scale of Rainy River, which cost New Gold $300 million in cash and scrip to buy, and is absorbing more than $1 billion to build, makes accessing the project’s full forecast $200 million or so of annual free cash flow critical.

Dual-listed (TSX/NYSE: HGD) New Gold has surged this year along with gold peers, up 114% since January 19. But its share price is down 35% from an August 10 high of US$5.94, and has drifted 32% lower since the start of last month. A softer gold price has also contributed to that but cornerstone project deliveries will sideline investors ahead of clear de-risking and de-bugging.

New Gold had a market capitalisation at the end of last week of $1.97 billion.

RBC confirmed Rainy River was about 55% complete and “on track for start-up in mid-2017”.

The bank’s analysts said New Gold recently accelerated heavy purchases of mobile fleet to ensure its material movement rates remained on schedule and ore stockpiling was on target. New Gold has said the doubling of the haul-truck fleet to 16 trucks and addition of a third mining shovel would enable it to lift its daily mining rate from 85,000 tonnes to 145,000t. It was aiming to pre-strip 45-50 million tonnes of overburden by mid-2017.

“The larger fleet also allows the pit to be opened up earlier, which should provide greater operational flexibility, including the ability to stockpile lower-grade material and reduce congestion in the pit during initial phases of production,” RBC’s analysts said.

“Mill construction [is] progressing well. Overall, the processing plant is now about 50% complete, with steelwork and concrete placement nearing the final stages, mill shells installed, and a majority of equipment purchased. The focus has shifted to installation of mechanical, piping, electrical and instrumentation in the plant.”

New Gold is also expecting receipt of its final tailings dam Schedule 2 permit in mid-2017, allowing it to complete the first tailings lift by October next year. But it is also building a starter dam with six months of holding capacity so the project timeline doesn’t hinge on the main dam permit.

“We expect Rainy River to drive material production growth for New Gold starting in mid-2017,” RBC said.

“With the project expected to benefit from low cost power, skilled/productive workforce and access to well-developed infrastructure/supply chains, we expect Rainy River to be a low cost producer.

“We expect the project's economics to be further enhanced through reserve and resource growth including addition of the Burns Block [Bayfield acquisition] and regional exploration.”

New Gold says deferral of the proposed $100 million underground development at Rainy River will better position it to “generate robust free cash flow once the mine begins production in mid-2017”.

“The combination of Rainy River’s location, average gold head grade of 1.5 grams per tonne over the first nine years, secured low power rates and predominantly Canadian dollar denominated operating costs is expected to result in below industry average all-in sustaining costs … [of] $710 per ounce over the first nine years of the mine life,” it said.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining News Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining News Intelligence team.

editions

Mining Company ESG Index: Benchmarking the Future of Sustainable Mining

The Mining Company ESG Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Journal Intelligence Global Leadership Report 2024: Net Zero

Gain insights into decarbonisation trends and strategies from interviews with 20+ top mining executives and experts plus an industrywide survey.

editions

Mining Journal Intelligence Project Pipeline Handbook 2024

View our 50 top mining projects, handpicked using a unique, objective selection process from a database of 450+ global assets.

editions

MiningNews.net Research Report 2024

Access a multi-pronged tool to identify critical risks and opportunities in Australia’s mining industry.