Scoping study outlines 25-year operation to revive historical South African mines

 WWI is focused on the Qala Shallow area initially

WWI is focused on the Qala Shallow area initially

While the thrust of WWI's immediate focus is on completing the Qala Shallows DFS before the end of the month, before shifting into project execution now that it has is long-sought approvals, the bigger picture for the WBP has started to come into focus.
 
Based on recovering 16 million tonnes grading three grams per tonne for 1.6 million ounces, the scoping study outlines an average steady state output of 80,000ozpa over 18 years, with peak production of 95,000oz in the eighth year.
 
The study focused on just part of a wider resource of 26Mt at 4.26gpt for 3.55Moz.
 
Managing director Jac van Heerden said the Witwatersrand Basin mines had historically yielded robust results, and he is confident it will do so again, as the initial Qala Shallows area in the Kimberley Reef package, is joined by the Main Reef package and Bird Reef East areas, starting from year three.
 
Step one of the plan is to commence with the rehabilitation and recommissioning of the existing box cut at the Qala shaft and widening of the decline to access the existing workings. The company can then gradually better assess other mining areas, as each reef package is subject to a targeted DFS. 
 
The shallows are expected to produce some 630,000oz at 3.4gpt over 13 years, starting from year two.
 
The Main Reef area is a higher-grade, shorter life package that will generate 105,000oz grading 5.3gpt over five years from year four, and could see the existing Number Six shaft opened.
 
Bird Reef East is the third development, before WWI brings in the lower-grade Bird Reef Central area, which is 3km further east.
 
Stage five is the Qala Deeps, from 500-1500m deep, and is nominally targeted from year 15.
 
Each area will be assessed for its idea access point, using existing shafts.
 
The project is located just 15km from Johannesburg's central business district.
 
WWI believes there is sufficient capacity and quality of processing in the region to enter a toll treating arrangement, rather than developing a standalone, company-owned facility.
 
The project was last operated by Durban Roodepoort Deep in the 1990s, before closure due to the low gold price in the early 2000s.
 
WWI's shares have traded between A2-15c over the past year, with the stock up 5% today to 6.1c, valuing it at $88 million.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining News Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining News Intelligence team.

editions

Mining Company ESG Index: Benchmarking the Future of Sustainable Mining

The Mining Company ESG Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Journal Intelligence Global Leadership Report 2024: Net Zero

Gain insights into decarbonisation trends and strategies from interviews with 20+ top mining executives and experts plus an industrywide survey.

editions

Mining Journal Intelligence Project Pipeline Handbook 2024

View our 50 top mining projects, handpicked using a unique, objective selection process from a database of 450+ global assets.

editions

MiningNews.net Research Report 2024

Access a multi-pronged tool to identify critical risks and opportunities in Australia’s mining industry.